Nokia SDM-2002001030 - SDM Certification - PS NSOP Exam
Page: 3 / 32
Total 160 questions
Question #11 (Topic: Topic 2)
What are the key responsibilities for CM Manager?
A. Network HW & SW Upgrades Management; Management of the network maintenance; Management of CM personnel; CM tools selection; CM procedure management; Correlation of CM procedures with PM and FM procedures.
B. SLA SOA content definition; Account Director support; Third party company management; End to End quality of service Management.
C. Leadership and Management; Network Configuration reporting; Network database maintenance; management of network acceptance and changes; maintenance and development of CM tools; change management procedures and templates; configuration integrity.
D. CM Procedure Management, CM Team Leadership; CM report creation; Network Planning; HW management.
Answer: C
Question #12 (Topic: Topic 2)
What BEST describe the CM process?
A. Configuration Management plans, manages and controls changes to the network & infrastructure, including acceptance, management & approval of work orders, documentation, data management and integrity.
B. Configuration Management controls all work orders and trouble tickets; manages and controls changes to the network.
C. Configuration Management manages and controls changes to the network & infrastructure, including acceptance, management & approval of work orders, analysis of trends in mobile networks.
D. Configuration Management plans, manages and controls changes to the network & infrastructure, including acceptance, management & approval of work orders, documentation, Trouble Ticket reporting, invoicing.
Answer: A
Question #13 (Topic: Topic 2)
What functions does the CM team support?
A. Supports Network Implementation, Hardware Management, Network set up & Network Operations at engineering meetings.
B. Supports the Hardware Management, Site Configuration, Configuration Management, Optimization.
C. Supports Report Management, Measurement Analysis, Fault identification, Fault Resolution.
D. Supports the Network Planning & Optimisation, Performance Management, Fault Management, Network Operations at Engineering meetings.
Answer: D
Question #14 (Topic: Topic 2)
Which are the main CM interfaces?
A. FM, PM, NOC management, Field maintenance management, NPO, customer and
vendors.
B. FM, PM, NOC management, Field maintenance management, SM.
C. PM, NOC management, Field maintenance management, NPO, SM.
D. FM, Care, NOC management, Field maintenance management, NPO.
A. FM, PM, NOC management, Field maintenance management, NPO, customer and
vendors.
B. FM, PM, NOC management, Field maintenance management, SM.
C. PM, NOC management, Field maintenance management, NPO, SM.
D. FM, Care, NOC management, Field maintenance management, NPO.
Answer: A
Topic 3, Cost Management
Question #15 (Topic: Topic 3)
What is the formula of the "value of risk" in the quantitative risk analysis?
A. = (The impact of risk in €) * (the probability of occurrence in %).
B. = (The cost of risk mitigation in €) * (the probability of occurrence in %).
C. = (The risk contingency budget in €) / (the probability of occurrence in %).
D. = (The cost of transferring the risk in €) / (the probability of occurrence in %).
Answer: A