Question #11 (Topic: Single Topic)
Which should be funded by a change budget?
A. Increase in agreed scope
B. Initiation stage
C. Change Authority
D. Handover activities
Answer: A
Question #12 (Topic: Single Topic)
Which should be funded from a change budget?
A. The Starting up a Project process
B. A fallback plan
C. An agreed change to the scope of a project
D. A change to a plan, within allocated tolerances, due to poor estimating
Answer: C
Question #13 (Topic: Single Topic)
Which is the Issue Register NOT used for?
A. Capture external events that are impacting a stage
B. Record information about a deviation in stage tolerance
C. Capture any threats or opportunities that might have an impact on a stage
D. Record any problems identified when authorizing a Work Package
Answer: C
Question #14 (Topic: Single Topic)
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
A. Checkpoint Report
B. Highlight Report
C. Issue Report
D. Product Status Account
Answer: C
Question #15 (Topic: Single Topic)
Which is the purpose of the Change theme?
A. To prevent change to baselined products
B. To identify, assess and control any potential and approved changes to baselined products
C. To establish mechanisms to monitor and compare actual achievements against those planned
D. To assess and control uncertainty
Answer: B