PRINCE2 PRINCE2-Foundation - PRINCE2 Foundation Exam

Question #6 (Topic: Single Topic)
What is an off-specification?
A. A new requirement B. A quality tolerance C. A type of issue D. A major risk
Answer: C
Question #7 (Topic: Single Topic)
Which is a type of issue?
A. A lesson B. A request for change C. An Exception Report D. A risk with an estimated high impact
Answer: B
Question #8 (Topic: Single Topic)
Which is a typical core activity within configuration management?
A. Quality assurance B. Risk management C. Verification and audit D. Progress reporting
Answer: C
Question #9 (Topic: Single Topic)
Which is a typical core activity within configuration management?
A. Issue management B. Quality inspection C. Identification D. Preparation
Answer: C
Question #10 (Topic: Single Topic)
What needs to be in place to ensure effective issue and change control?
A. Configuration management system B. Manage by exception C. Quality planning D. Information needs for stakeholders
Answer: A
Download Exam
Page: 2 / 107
Total 534 questions