Question #11 (Topic: Topic 1)
You are managing a project that will implement a new Insurance software package. Two
project team members have difficulty working together. They come to you, for help
resolving the issues. You immediately set up a meeting that includes the functional
manager. After the meeting you and the functional manager discuss the issues and agree
on a solution. What type of organizational structure you are working in?
project team members have difficulty working together. They come to you, for help
resolving the issues. You immediately set up a meeting that includes the functional
manager. After the meeting you and the functional manager discuss the issues and agree
on a solution. What type of organizational structure you are working in?
A. Functional
B. Balanced matrix
C. Piojectized
D. Strong Matrix
Answer: B
Question #12 (Topic: Topic 1)
You have been with the organization; you constantly hear rumours about a certain CAPM
failing to live up to the CAPM Code. What you should do?
failing to live up to the CAPM Code. What you should do?
A. You can gather as much information as you can before proceeding
B. Confront the person immediately
C. Ignore the rumours
D. ^ass the rumours along
Answer: A
Question #13 (Topic: Topic 1)
Who is responsible for issuing the project charter?
A. The project manager
B. The project sponsor
C. The Team lead
D. The nianagement
Answer: B
Question #14 (Topic: Topic 1)
In PMBOK, the seller is ________ to the project team.
A. Internal
B. External
C. Outside
D. Assigned
Answer: B
Question #15 (Topic: Topic 1)
Project Quality Management includes:
A. Customer satisfaction
B. Prevention over inspection
C. Continuous improvement
D. Al1 of the above
Answer: D