PMI PMI-002 - Certified Associate in Project Management (CAPM) Certification Exam
Page: 2 / 150
Total 748 questions
Question #6 (Topic: Topic 1)
Which of the following provides the least accurate in estimating?
A. Rough order of magnitude
B. Budget estimate
C. WBS estimate
D. Definitive estimate
Answer: A
Question #7 (Topic: Topic 1)
Who has the responsibility for informing the final deliverable to all stakeholders?
A. Project Manager
B. Sponsor
C. Team Lead
D. Management
Answer: A
Question #8 (Topic: Topic 1)
What is a corrective action?
A. An action that brings future project events Into alignment with the project plan
B. An action to correct something in the project
C. An action to prevent something in the project
D. Corrective action is not related to project
Answer: A
Question #9 (Topic: Topic 1)
Assumptions are factors that, for planning purposes, are considered to be ______.
A. True, real, or certain
B. True, real, or uncertain
C. Real
D. Verbal
Answer: A
Question #10 (Topic: Topic 1)
A complete set of indexed project records is called __________.
A. Project archives
B. Index
C. sow
D. Project History
Answer: A