Question #1 (Topic: Topic 1)
A contract cannot contain _____________.
A. Illegal activities B. deadline for the completion of the work C. Penalties and fines for disclosure of intellectual rights D. Al1 of the above
Answer: A
Question #2 (Topic: Topic 1)
Which one of the following comes first in the project plan?
A. Scope Statement B. Quality Plan C. WBS D. Development Plan
Answer: A
Question #3 (Topic: Topic 1)
You are project manager of a project. During the process of selecting the sellers, you reject
one vendor because it doesn't have the manufacturing capability. This is an example of
which selection tool?
A. Weighting system B. Screening system C. Seller rating system D. Expert judgment
Answer: B
Question #4 (Topic: Topic 1)
______________ provides details about how the project scope may be changed.
A. Control Scope system B. VeiirV Scope C. Scope Charter D. Scope Management plan
Answer: D
Question #5 (Topic: Topic 1)
Which of the following technique to identify the underlying cause of a problem and take
steps to prevent further occurrence?
A. Root cause analysis B. Quality audits C. Project audits D. Risk audits
Answer: A