CompTIA PK0-003 - CompTIA Project+ Certification Exam

Question #11 (Topic: Topic 1)
A project starts out as a small three month project. One month into the project, a
stakeholder asks the team for additional functionality, which is estimated to take an
additional three weeks. The project manager implements the functionality while waiting for
approval. This is known as which of the following?
A. Change request B. Risk C. Resource constraint D. Scope creep
Answer: D
Question #12 (Topic: Topic 1)
Within a corporation, project managers are assigned people based on defined roles and
responsibilities. Project resources are temporarily provided to the project but still report the
functional managers as well as the project manager. Which of the following styles of
management is this also known as?
A. Projectized management B. Matrix management C. Functional management D. SCRUM / agile
Answer: B
Question #13 (Topic: Topic 1)
In the planning phase of a project, which of the following activities is performed?
A. Solicitation B. Perform a feasibility study C. Appoint a project team D. Project Charter
Answer: C
Question #14 (Topic: Topic 1)
A project manager will initially baseline a project when:
A. change requests are approved. B. stakeholders request project initiation. C. creating a project charter. D. tasks and estimates have been identified.
Answer: D
Question #15 (Topic: Topic 1)
Which of the following risk responses would be characterized by having knowledge of a risk
event and taking advantage of the risk?
A. Accepting B. Enhancing C. Exploiting D. Sharing
Answer: C