Question #6 (Topic: Topic 1)
A project is a (an):
A. specific solution. B. business strategic plan. C. group of products. D. ongoing endeavor.
Answer: A
Question #7 (Topic: Topic 1)
Which of the following would be found in a post-mortem analysis? (Select TWO).
A. Lessons Learned B. Transition Plan C. Project sponsor signoff D. Maintenance responsibilities E. Reasons for early termination of the project
Answer: A,E
Question #8 (Topic: Topic 1)
The project charter contains a list of project limitations also known as:
A. variances. B. constraints. C. assumptions. D. milestones.
Answer: B
Question #9 (Topic: Topic 1)
In a project kick-off meeting, the project manager does which of the following?
A. Discusses pending change requests B. Obtains approval on the budget C. Receives buy in from the stakeholders D. Reviews the project goals
Answer: D
Question #10 (Topic: Topic 1)
Which of the following is a characteristic of a project stakeholder?
A. Someone who approves deliverables B. Someone who approves contractors C. Someone who is a C level manager D. Someone who approves purchase orders
Answer: A