A change request has been authorized to decrease the amount of time the project team has to hand over the deliverable to the customer. The project manager has decided to crash the schedule to accommodate the change. Which of the following will MOST likely occur?
Answer : C
The project manager wants to report to the stakeholders to date projects cost performance. If the total of completed work to date is $200,000 and the actual cost is
$210,000, which of the following is the cost variance?
Answer : C
Which of the following steps is required to validate a business case?
Answer : A
A project team has to implement a key part of their solution from an external vendor. After sending out an RFP, the team has narrowed the possible providers down to three. Which of the following should the project manager do NEXT?
Answer : A
In QC testing, the project manager determines that the deliverable is outside of the specification limits. Which of the following processes allowed the project manager to make this determination?
Answer : D
Prior to a project kick-off, the project manager should do which of the following?
Answer : A
Which of the following is a characteristic of a product life cycle?
Answer : C
Which of the following is the purpose of a post mortem analysis?
Answer : D
The Earned Value of a project for the month is $10,000, and the Actual Cost of the project was $8,000. Which of the following is the Cost Performance Index?
Answer : D
The project team is one month away from completing the project when a vendor that is providing a key component defaults on their contract. Which of the following is the FIRST thing the project manager should do?
Answer : B
A project manager was informed that a task will be delayed by four weeks. To determine the impact on the overall project, which of the following will the project manager need to update FIRST?
Answer : C
While working on a project, an unforeseen event arises that impacts a project objective.
Which of the following should be updated as a result?
Answer : B
Which of the following types of organizational structures groups personnel by both functions and projects?
Answer : D
A project team is about to deliver on a two year long project when they are informed of new
Government laws that directly affect the product. The team meets with their stakeholders to discuss the impact to the project and determine that additional laws need to be taken into account before go-live. The NEXT step the project manager needs to take is:
Answer : B
The project team is geographically split between two time zones. Which of the following should be performed by the project manager?
Answer : B