CompTIA PK0-003 - CompTIA Project+ Certification Exam
Page: 1 / 60
Total 298 questions
Question #1 (Topic: Topic 1)
Which of the following process groups of the project life cycle integrates people and other
resources to carry out the work defined in the project plan?
resources to carry out the work defined in the project plan?
A. Executing
B. Planning
C. Closing
D. Initiating
Answer: A
Question #2 (Topic: Topic 1)
When performing quantitative risk analysis, which of the following should be produced?
A. Control chart
B. Decision tree
C. Run chart
D. Scatter diagram
Answer: B
Question #3 (Topic: Topic 1)
After identifying a change needed in the system, which of the following is the NEXT action
the stakeholder should perform?
the stakeholder should perform?
A. Inform the developer
B. Inform the resource manager
C. Inform the project manager
D. Inform the project sponsor
Answer: C
Question #4 (Topic: Topic 1)
A project is experiencing quality issues with the deliverable product. Which of the following
tools would be used to identify and prioritize the MOST commonly occurring issues?
tools would be used to identify and prioritize the MOST commonly occurring issues?
A. Scatter diagram
B. Pareto chart
C. Ishikawa diagram
D. Trend analysis
Answer: B
Question #5 (Topic: Topic 1)
When a project manager is leading the team through the norming stage of team growth, the
project team:
project team:
A. is performing in a highly efficient manner.
B. has reached full capacity.
C. is seeing a decrease in productivity.
D. is working together and comfortable.
Answer: D