Nokia PDM-2002001060 - CPM Exam

Question #11 (Topic: )
Which of the following documents are NOT part of the PTA handover from Sales to
Delivery?
A. Cost baseline. B. Project management/delivery plan. C. Logistics plan. D. WBS structure.
Answer: D
Question #12 (Topic: )
When should risk analysis be performed?
A. Just before any major meeting with the client. B. On a regular basis prior to and throughout the project. C. Only when justified by the awareness of new risks becoming a possibility. D. When preparing the project plan.
Answer: B
Question #13 (Topic: )
Decomposing the major deliverables into smaller, more manageable components to
provide better control is called:
A. scope planning. B. scope definition. C. scope baselining. D. scope verification.
Answer: B
Question #14 (Topic: )
In which of the following items are the contents of the VOA used in SAP?
A. Sales order. B. Service order. C. Quantity contract. D. Customer invoice.
Answer: B
Question #15 (Topic: )
Company A is working on a project. The projects budget is 10,000. The Planned value as
of date X is 4,000. The project is 30% completed. 60% of the budget has been spent. If
the company continues to spend money at the same rate, what will the project cost (EAC)?
A. €10,000. B. €20,000. C. €6,000. D. €4,000.
Answer: B