Nokia PDM-2002001060 - CPM Exam

Question #6 (Topic: )
At a given point in time, a project has a CPI = 0.7 and SV = €1,000. The project is:
A. over budget and ahead of schedule. B. over budget and behind schedule. C. below budget and ahead of schedule. D. below budget and behind schedule.
Answer: A
Question #7 (Topic: )
The best way to manage the costs of change requests is to:
A. accept them verbally. B. allow them to happen in an ad-hoc fashion. C. impose change unilaterally. D. document and authorize all changes.
Answer: D
Question #8 (Topic: )
What is a liable party?
A. The party responsible for approving a change. B. The party responsible for implementing a change. C. The party responsible for bearing the costs of a change. D. The party initiating a change request.
Answer: C
Question #9 (Topic: )
Which of the following are key components of a Site Process?
A. Acceptance milestones, share of responsibilities and invoicing triggers. B. Change management process and communication plan. C. Master schedule, WBS and rollout plan. D. Work Packages, WBS and invoicing triggers.
Answer: A
Question #10 (Topic: )
Company A is working on a project. The projects budget is 10,000. The planned value as
of date X is 4,000. The project has an earned value of 3,500 and actual costs of 4,500.
Which statement is correct?
A. The project is behind schedule. B. The project is ahead of schedule. C. The project is finished. D. The project is on schedule.
Answer: A