If a customer requests a consistency check to the network design, which was not included in Nokia scope of work, what is the appropriate action?
Answer : B
What of the following is NOT part of the root cause analysis process?
Answer : B
What is the duration of short term planning (STP) period?
Answer : B
Which of the following cost components are allocated to a non-site level WBS element?
Answer : B
Nokia orders the I&C from a subcontractor. The subcon, not completely familiar with this new equipment, requires a Nokia technician to complete the service. What is the correct way to proceed?
Answer : C
Which of the following contract types places the greatest risk on the seller?
Answer : D
If Net Sales are €150 and Cost of Goods Sold are €100, what is the Gross Profit in %?
Answer : D
Internal acceptance is a milestone that will trigger:
Answer : B
Before which approval gate do you have greatest possible influence on risks and the related costs?
Answer : A
What will be the resulting performance index if the actual cost is higher than the earned value?
Answer : C
A __________ is a formal invitation to submit a price for goods and/or services as specified:
Answer : A
A project risk is a(n) __________ event or condition that, if it occurs, has a ___________ effect on at least one project objective:
Answer : C
Which one of the following is NOT a risk?
Answer : C
The project team has received the LoA approved risk log, which is the basis for the cost baseline risk contingency. During project execution a new relevant risk is identified. What is the best way to manage it?
Answer : A
What is the purpose of a Project Target Agreement (PTA)?
Answer : A