Microsoft MB5-705 - Managing Microsoft Dynamics Implementations Exam

Question #11 (Topic: )
Which document is used in the Microsoft Dynamics Sure Step Methodology to document
project risks?
A. risk category B. risk register C. risk response strategies D. risk analysis
Answer: B
Question #12 (Topic: )
What is the maximum time allocated to a developer task within a sprint cycle?
A. 8 hours B. 16 hours C. 1 day D. 30 days
Answer: B
Question #13 (Topic: )
You need to create a project by using the Sure Step Project Creation Wizard.
Which two properties must you identify in order to proceed? (Each correct answer presents
part of the solution. Choose two.)
A. engagement type B. product C. project implementation phase D. product version
Answer: A,B
Question #14 (Topic: )
You are a project manager for a technology consulting company.
Your team is finalizing a commercial engagement proposal for presentation and sign-off.
In conjunction with the engagement manager, you need to provide details for the proposal.
Which two details should you provide? (Each correct answer presents part of the solution.
Choose two.)
A. functional details B. project scope details C. technical details D. the licensing and service contract agreements E. the statement of work
Answer: D,E
Question #15 (Topic: )
You are a project manager. You use the classic triple constraint model. If one constraint is
changed, what happens to the other constraints?
A. The project's quality constraint will change. B. The project's expectations constraint will change. C. At least one of the other constraints must also change. D. The customer's benefits constraint will change.
Answer: C