Microsoft MB5-705 - Managing Microsoft Dynamics Implementations Exam

Question #6 (Topic: )
Which two activities are included in the Fit Gap and Solution Blueprint process flow? (Each
correct answer presents part of the solution. Choose two.)
A. Generate an implementation plan report. B. Lead requirements workshops with product demos. C. Conduct a project kickoff meeting. D. Configure a subset of business requirements.
Answer: A,D
Question #7 (Topic: )
You are delivering a project by using the waterfall delivery method.
You approve the project charter and project plan.
Which three actions should you do next? (Each correct answer presents part of the
solution. Choose three.)
A. Document the configuration of the overall Microsoft Dynamics solution. B. Create the deployment plan. C. Perform and document the Fit Gap Analysis. D. Complete the design specifications. E. Develop future state business process models. F. Conduct the Executive and Project Team kickoff meetings.
Answer: C,E,F
Question #8 (Topic: )
What is an objective of diagnostic preparation?
A. to lead an internal kickoff meeting B. to gain a preliminary understanding of the customer's needs C. to plan the running of diagnostic accelerators D. to prepare high-level project documents
Answer: B
Question #9 (Topic: )
You need to create a proposal for the final licensing and services agreement.
Which two roles should be involved in creation of the proposal? (Each correct answer
presents part of the solution. Choose two.)
A. account manager B. project manager C. sales representative D. engagement manager
Answer: B,D
Question #10 (Topic: )
Which project types does the Microsoft Dynamics Sure Step Model use?
A. waterfall, iterative B. diagnostic, analysis, design, development, deployment, and operation C. standard, rapid, enterprise, agile, and upgrade D. diagnostic, development, and operational
Answer: C