CompTIA JK0-017 - CompTIA E2C Project+ Certification Exam Exam

Question #11 (Topic: Topic 1)
In order to obtain the best pricing and product quality, a project manager should:
A. obtain an RFP from one vendor who can provide the products. B. obtain an RFP from the vendor who provides the lowest priced products. C. obtain responses from different vendors to compare the products. D. use past vendors who have provided all project deliverables.
Answer: C
Question #12 (Topic: Topic 1)
A project manager has decided to increase the number of resources working on critical
path activities. This is an example of:
A. rolling wave planning. B. resource leveling. C. fast tracking. D. crashing.
Answer: D
Question #13 (Topic: Topic 1)
Which of the following may have a significant adverse impact upon the successful
completion of an international project? (Select Three).
A. Time zones B. Travel costs C. Co-location of resources D. The project plan E. Scheduled vacations F. Language barriers
Answer: A,B,F
Question #14 (Topic: Topic 1)
A project manager is presented with a change request for an ongoing project. Which of the
following would be the FIRST action?
A. Update the project plan to accommodate the changes. B. Perform an impact analysis. C. Organize a stakeholder meeting to review the changes. D. Change the project scope to reflect the change request.
Answer: B
Question #15 (Topic: Topic 1)
Which of the following are created using information contained in the work breakdown
structure (WBS)? (Select Two).
A. Project scope statement B. Project statement of work C. Project charter D. Project activity estimates E. Project resource estimates
Answer: D,E