Question #6 (Topic: Topic 1)
Which of the following is true of fast tracking a schedule?
A. Project schedule critical path will change.
B. Project activities will be performed concurrently.
C. Project schedule is shortened by decreasing the project scope.
D. Project schedule lead times are increased.
Answer: B
Question #7 (Topic: Topic 1)
A project team member is uncertain how many activities are required to complete a task.
Which of the following documents should be referenced?
Which of the following documents should be referenced?
A. Key Performance Indicators (KPIs)
B. Project charter
C. Work Breakdown Structure (WBS)
D. Statement of Work (SOW)
Answer: C
Question #8 (Topic: Topic 1)
Which of the following is the BEST communication option for team building?
A. Send an email transmission to introduce the project.
B. Send a completed project charter to introduce the project.
C. Leave a voicemail message to introduce the project.
D. Schedule a face-to-face meeting to introduce the project.
Answer: D
Question #9 (Topic: Topic 1)
Which of the following is created using the work breakdown structure (WBS) as an input?
A. Procurement management plan
B. Vendor selection criteria
C. Project scope statement
D. Project charter
Answer: A
Question #10 (Topic: Topic 1)
A cause and effect diagram can also be called:
A. a control chart.
B. a scatter diagram.
C. an Ishikawa diagram.
D. a Pareto Chart.
Answer: C