Which of the following techniques can a project manager use to assist with quality planning? (Select Three).

  • A. Peer review
  • B. Critical Chain Method (CCM)
  • C. Inspection
  • D. Performance Evaluation and Review Technique (PERT)
  • E. Work Breakdown Structure (WBS)
  • F. Benchmarking


Answer : A,C,F

All of the following are part of the monitoring and controlling process group EXCEPT:

  • A. updating the project charter.
  • B. updating the project management plan.
  • C. implementing change requests.
  • D. updating the project scope.


Answer : A

After identifying the activities in a work package, which of the following is the NEXT step that a project manager should complete?

  • A. Estimate costs
  • B. Identify activities
  • C. Build a project schedule
  • D. Assign key stakeholders


Answer : A

In which of the following organization types would a project manager have the LEAST amount of project authority?

  • A. Functional
  • B. Strong Matrix
  • C. Balanced Matrix
  • D. Weak Matrix


Answer : A

A project manager was asked to complete a project three weeks early and not crash the project. Which of the following should be done?

  • A. Move some of the task to another release.
  • B. Have the team work over time and give them time off later to save the budget.
  • C. Continue to work and complete the project as soon as possible.
  • D. Review the plan with the team and develop a way to reduce the time


Answer : D

The work breakdown structure (WBS) dictionary contains which of the following elements?
(Select Three).

  • A. Identification of stakeholders
  • B. Description of work processes and procedures
  • C. Quality control processes
  • D. Estimated calendar time of activities
  • E. Required resources
  • F. Risk response strategies


Answer : B,D,E

One of the team members assigned to a project is not performing well. The team member is new and is not experienced in the type of work involved with this project. Which of the following is the BEST response to this situation?

  • A. Ask other team members to help.
  • B. Assign the team member to another project.
  • C. Talk to the team member to encourage better performance.
  • D. Arrange for training for the team member.


Answer : D

A stakeholder has determined the need to update their payroll method with a new system.
Which of the following is the FIRST activity the corporation should perform?

  • A. Conduct a feasibility study.
  • B. Determine the justification of the project.
  • C. Obtain a preliminary review by the project selection committee.
  • D. Determine if the project is in alignment with the companys strategic plan.


Answer : D

A project manager is performing activity duration estimation. This project will have conditional decisions. Which of the following tools would be the BEST to use?

  • A. GERT
  • B. Gantt chart
  • C. PERT
  • D. EVM


Answer : A

A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?

  • A. Transition plan
  • B. Quality plan
  • C. Change Control plan
  • D. Procurement plan


Answer : A

Which of the following tools would be used to determine the relationship between two changed variables?

  • A. Scatter diagram
  • B. Qualitative risk analysis
  • C. Ishikawa diagram
  • D. Monte Carlo analysis


Answer : A

Which of the following is included in the project charter?

  • A. A work performance report
  • B. A cost assessment
  • C. A high level plan
  • D. A risk assessment


Answer : C

Refer to the attached Exhibit.
Which of the following is the float of path Start-C-E-Finish in the network diagram?

  • A. Zero
  • B. One
  • C. Three
  • D. Five


Answer : A

After final acceptance, which of the following would the project manager use to assess the strengths and weaknesses of the project?

  • A. Post-project review
  • B. Transition plan
  • C. Project kick-off meeting
  • D. Quality analysis


Answer : A

Which of the following is used to display a project schedule?

  • A. Gantt chart
  • B. Work Breakdown Structure (WBS)
  • C. Pareto chart
  • D. Ishikawa diagram


Answer : A