GIAC GCPM - GIAC Certified Project Manager Exam

Question #11 (Topic: Volume A)
FILL BLANK
Fill in the blank with the appropriate term.
______________________ involves the implementation of strategies to reduce the negative aspects of conflict and to increase the positive aspects of conflict at a
level equal to or higher than where the conflict is taking place.
Answer: Conflict management
Question #12 (Topic: Volume A)
Lamont is the project manager of a project that has recently finished the final project deliverables. The project customer has signed off on the project deliverable
and Lamont has a few administrative closure activities to complete. In the project, there were several large risks that could have wrecked the project but Lamont
and his project team found some creative methods to resolve the risks without affecting the project costs or project end date. What should Lamont do with the risk
responses he identified during the project's monitoring and controlling process?
A. Include the risk response in the project risk management plan. B. Include the risk responses in the organization's lessons learned database. C. Nothing. The risk responses are included in the project's risk register already. D. Include the responses in the project management plan.
Answer: A
Question #13 (Topic: Volume A)
You are the project manager for your organization. Marcy, a project stakeholder, is demanding that you add some deliverables to your project scope for free. You
explain to Marcy that it's too late in the project execution to consider adding these deliverables, as most of the software your project team is creating is nearly
done. Marcy and you escalate the issue to management. Management decides that you will add the deliverables to the project scope if Marcy pays a significant
fee and allows you additional time to complete the project. What conflict resolution method has management offered?
A. Confronting B. Compromising C. Forcing D. Issue management
Answer: A
Question #14 (Topic: Volume A)
You are project manager of HHK project. Examine the network diagram given below:
[GIAC-GCPM-1.0/xmlfile-15_1.png]
A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days
can Activity E be delayed?
A. Six days B. Zero, it is on the critical path. C. Four days D. Five days
Answer: C
Question #15 (Topic: Volume A)
You work as a project manager for HRM Inc. You want to communicate and solicit feedback from your employees to build future plans. Which of the following will
help you to accomplish the above task?
A. Change register B. Risk register C. Organizational chart D. Stakeholders register
Answer: C