Question #6 (Topic: Volume A)
Which of the following is defined as the time it takes to complete a task or a set of interdependent tasks?
A. Lag time B. Mean time C. Fixed time D. Lead time
Answer: C
Question #7 (Topic: Volume A)
You work as a project manager for HRM Inc. You are performing steps to carry out and finish the project according to the measures drawn through the planning
stage. Which of the following stages of the project are you working on?
A. Initiation B. Monitoring and controlling C. Execution D. Closing
Answer: C
Question #8 (Topic: Volume A)
Which of the following are the tools and techniques of the Plan Procurement Management process?
Each correct answer represents a complete solution. Choose three.
A. Probability and impact matrix B. Make-or-buy analysis C. Expert judgment D. Market research
Answer: BCD
Question #9 (Topic: Volume A)
Tom is the project manager for his organization and he's creating a project network diagram for this project. He has created his project network diagramming with
the consideration of the availability of project resources. What network diagramming approach has Tom used in this example?
A. Critical path method B. Critical chain method C. Activity on the arrow D. Fast tracking
Answer: B
Question #10 (Topic: Volume A)
You are using the PDCA model to determine, implement, monitor, control, and maintain Information Security Management System or ISMS. You have to evaluate
the new processes and match up to the results against the probable results to determine the differences. In which of the following phases of the PDCA are you
working?
A. Check B. Plan C. Act D. Do
Answer: A