Question #11 (Topic: Topic 1)
Which of the following statements best explains what the term Sprint means in Scrum?
A. A sprint is a specific amount of days for a team to test and resolve any issues prior to product release or shipment B. A sprint is a specific amount of days for a team to work at a sustainable pace to finish select work. C. A sprint is an agreed upon period of time for team members to select individual items from the product backlog to work on. D. A sprint is a specific amount of days for a team to work as many hours as needed to finish assigned work
Answer: B
Question #12 (Topic: Topic 1)
_____________ can change the priority of items in the _________ backlog at any time.
A. The Team; Product B. The Product Owner(s); Sprint C. The Product Owner(s); Product D. The Scrum Master; Sprint
Answer: C
Question #13 (Topic: Topic 1)
Which of the following is not a Scrum cycle activity?
A. Sprint retrospective B. Daily scrum C. Weekly inspection D. Sprint planning
Answer: C
Question #14 (Topic: Topic 1)
Which of the following statements best describes Product Backlog items?
A. Undefined or poorly defined Product Backlog items should be placed on the Product Backlog with a low priority B. All Product Backlog items are the result of a(n) analysis, requirements and/or design phase(s). C. Undefined or poorly defined Product Backlog items should be kept out from the Product Backlog until sufficient detail is known. D. Every Product Backlog item, whether low priority or high priority, should possess sufficient detail for the Team to complete in a Sprint.
Answer: C
Question #15 (Topic: Topic 1)
________________ constitute the Sprint Backlog and are often estimated in hours?
A. User Stories B. Use Cases C. Features D. Tasks
Answer: D