GAQM CSM-001 - Certified Scrum Master Exam

Question #6 (Topic: Topic 1)
The Scrum Framework encompasses rules or guidelines for documentation?
A. True B. False
Answer: B
Question #7 (Topic: Topic 1)
The individual, detailed pieces of work that are needed to convert a product backlog item into a working software component or solution are called:
A. User Stories B. Use cases C. Line items D. Tasks
Answer: D
Question #8 (Topic: Topic 1)
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
A. The development team cannot meet their Sprint commitment to complete work if requirements are changing B. A Sprint cycle is not enough time for senior management review and approve changes C. This forces Product Owners to focus on what is really important for the team to develop. D. The development team must be able to limit the Product Owner authority
Answer: C
Question #9 (Topic: Topic 1)
Which of the following is not a Scrum artifact?
A. User Stories B. Sprint Backlog C. Product Backlog D. Software Increment
Answer: A
Question #10 (Topic: Topic 1)
You are the new Scrum Master at a company currently doing RUP in three month iterations. Your current task in switching from RUP to Scrum is to define how
long the Sprint cycle should be. In what units of time should you define the sprint cycle?
A. A fixed amount of months B. A fixed amount of weeks, excluding holidays C. A fixed amount of days D. A fixed amount of hours
Answer: C