Question #11 (Topic: Topic 1)
What is one of the MAJOR outputs of activity sequencing?
A. Responsibility assignment matrix
B. Work breakdown structure update
C. Project network diagram
D. Mandatory dependencies list
Answer: C
Question #12 (Topic: Topic 1)
Scope verification is PRIMARILY concerned with which of the following?
A. Acceptance of the work deliverables.
B. Accuracy of the work deliverables.
C. Approval of the scope statement.
D. Accuracy of the work breakdown structure.
Answer: A
Question #13 (Topic: Topic 1)
Which of the following is an example of contract administration?
A. Negotiating the contract
B. Authorizing contractor work
C. Developing the statement of work
D. Establishing evaluation criteria
Answer: B
Question #14 (Topic: Topic 1)
Who MUST know when a risk event occurs so that a response can be implemented?
A. Customers
B. Project sponsors
C. Project management team
D. Insurance claims department
Answer: C
Question #15 (Topic: Topic 1)
A work package has been scheduled to cost $1,000 to complete, and was to be finished
today. As of today, the actual expenditure is $1,200 and approximately half of the work has
been completed.
What is the cost variance?
today. As of today, the actual expenditure is $1,200 and approximately half of the work has
been completed.
What is the cost variance?
A. -$700
B. -$200
C. +$200
D. +$500
Answer: B