Question #6 (Topic: Topic 1)
Information distribution involves making needed information available to project
stakeholders in a timely manner. What is an output from information distribution?
stakeholders in a timely manner. What is an output from information distribution?
A. Earned value analysis
B. Trend analysis
C. Project records
D. Performance reviews
Answer: C
Question #7 (Topic: Topic 1)
Which type of analysis is used to examine project results through time to determine if
performance is improving or deteriorating?
performance is improving or deteriorating?
A. Control chart
B. Earned value
C. Variance
D. Trend
Answer: D
Question #8 (Topic: Topic 1)
You are assigned to implement the project control plan. What should you do to ensure the
plan is effective and current?
plan is effective and current?
A. Perform periodic project performance reviews.
B. Identify quality project standards.
C. Follow ISO 9000 quality standards
D. Complete the quality control checklist.
Answer: A
Question #9 (Topic: Topic 1)
Which of the following is an example of a risk symptom?
A. Failure to meet intermediate milestones
B. Force of nature, such as a flood
C. Risk threshold target
D. Crashing front loading or fast tracking
Answer: A
Question #10 (Topic: Topic 1)
During what process is the quality policy determined?
A. Initiating
B. Executing
C. Planning
D. Controlling
Answer: C