Question #1 (Topic: Topic 1)
On what is project baseline development established?
A. Approved product requirements B. Estimated project cost and schedule C. Actual project cost and schedule D. Revised project cost and schedule
Answer: B
Question #2 (Topic: Topic 1)
Identifying major deliverables, deciding if adequate cost estimates can be developed, and
identifying tangible components of each deliverable are all part of which of the following?
A. Work breakdown structure B. Organizational breakdown structure C. Resource breakdown structure D. Bill of materials
Answer: A
Question #3 (Topic: Topic 1)
What is the definition of project plan execution?
A. Integrating all planned activities. B. Performing the activities included in the plan. C. Developing and maintaining the plan. D. Execution of deliverables.
Answer: B
Question #4 (Topic: Topic 1)
What is a tool to improve team performance?
A. Staffing plan B. External feedback C. Performance reports D. Co-Location
Answer: D
Question #5 (Topic: Topic 1)
Which type of analysis is used to develop the communications management plan?
A. Product B. Cost benefit C. Stakeholder D. Research
Answer: C