SAP C_TSCM42_65 - SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP5 Exam

Question #11 (Topic: )
In SAP ECC, you calculate the standard available capacity for a work center capacity using
the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
A. 7 hours B. 6.16 hours C. 5.6 hours D. 8 hours
Answer: C
Question #12 (Topic: )
For which of the following objects can you enter a confirmation? (Choose two)
A. Production order B. Production order operation C. Trigger Point D. Work Center
Answer: A,B
Question #13 (Topic: )
When modeling in-house production using SAP ECC, on which business levels can you
create a bill of material (BOM)? (Choose two)
A. At the client level B. At the plant level C. At the company code level D. At the business area level
Answer: A,B
Question #14 (Topic: )
What could be a consequence of the confirmation of an operation?
A. Settlement of the actual costs B. Reduction of capacity requirements C. Rescheduling of the production order D. Update of the planned costs
Answer: B
Question #15 (Topic: )
In which master data object do you set the standard values for an operation?
A. Work Center B. Production Resource/Tool (PRT) C. Material Master D. Routing
Answer: D
Download Exam
Page: 3 / 16
Total 80 questions