SAP C_TSCM42_65 - SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP5 Exam
Page: 2 / 16
Total 80 questions
Question #6 (Topic: )
Which functions can be triggered before releasing a production order? (Choose three)
A. Confirmation
B. Selection of a routing
C. Scheduling
D. Stock determination
E. Selection of a BOM
Answer: B,C,E
Question #7 (Topic: )
What is a feature of the simu-lation mode for material requirements planning in SAP ECC?
A. It posts planning results to the database automatically.
B. It propagates exception messages from a component to the finished product.
C. It calculates the delay time which may occur in planning.
D. It triggers multilevel bottom-up scheduling.
Answer: C
Question #8 (Topic: )
Which of the following functions does SAP Supply Chain Management (SCM) offer?
A. Planning and optimization of supply chains across company boundaries.
B. Optimization of the procurement strategy with the supplier pool.
C. Product development, safety, quality, and maintenance.
D. Communication to customers through different interaction channels.
Answer: A
Question #9 (Topic: )
What sequence do you follow in master data maintenance to define the production of a
material?
material?
A. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing
B. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
C. Create routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or routing
D. Create work centers -> Create routing -> Create BOM -> Carry out component assignment in work center
Answer: A
Question #10 (Topic: )
In what sequence are the steps of material requirements planning performed in SAP ECC?
A. 1. Net requirements calculation 2. Lot sizing 3. Scheduling 4. Determination of the procurement type
B. 1. Calculation of safety stock 2. Lot sizing 3. Scheduling 4. Determination of the procurement type
C. 1. Net requirements calculation 2. Lot sizing 3. Determination of the procurement type 4. Scheduling
D. 1. Availability check 2. Lot sizing 3. Determination of the procurement type 4. Scheduling
Answer: C