Question #11 (Topic: Exam A)
Your team switched to using story points for estimation in the last 2 months and their sprints are 2 weeks long.
Which chart can definitely help you determine the average effort that the team can deliver during each sprint?
Which chart can definitely help you determine the average effort that the team can deliver during each sprint?
A. Velocity Chart
B. Cumulative Flow Diagram
C. Burnup Chart
D. Burndown Chart
Answer: A
Question #12 (Topic: Exam A)
The team requests that you configure their Kanban board in such a way that they can:
see just particular subsets of issues based on values in a radio button field
see all issues grouped by the epic they belong to
distinguish cards visually based on their priority
Select three board configurations that when combined together, will satisfy these requirements. (Choose three.)
see just particular subsets of issues based on values in a radio button field
see all issues grouped by the epic they belong to
distinguish cards visually based on their priority
Select three board configurations that when combined together, will satisfy these requirements. (Choose three.)
A. card colors by priority
B. board sub-filter based on radio button field
C. swimlanes by epic
D. card layout by priority
E. quick filters based on radio button field
F. quick filters based on epic
Answer: ACE
Question #13 (Topic: Exam A)
You manage two team-managed Scrum projects.
You want to create a single board that displays the progress of the active sprints in both projects and their burndown.
Identify the correct board type to use.
You want to create a single board that displays the progress of the active sprints in both projects and their burndown.
Identify the correct board type to use.
A. team-managed Scrum board
B. company-managed Kanban board
C. company-managed Scrum board
D. team-managed Kanban board
Answer: C
Question #14 (Topic: Exam A)
You want to configure a Kanban board so that issues disappear from the Done column as soon as they are dragged into it. But you need to see Done issues in reports.
How can you achieve this behavior?
How can you achieve this behavior?
A. modify a quick filter
B. modify the board filter
C. modify workflow status names
D. modify the unmapped statuses
E. modify the board sub-filter
Answer: E
Question #15 (Topic: Exam A)
You are the project administrator for a team based in the Middle East.
You need to change the Standard Working Days configuration on the board: from Sunday to Thursday instead of Monday to Friday.
What will be affected by this change?
You need to change the Standard Working Days configuration on the board: from Sunday to Thursday instead of Monday to Friday.
What will be affected by this change?
A. Velocity Chart
B. sprint duration
C. Average Age Report
D. original estimates on issues
E. Burndown Chart
Answer: E