Question #6 (Topic: Exam A)
Teams using Project A and B currently use their own respective Scrum boards.
They must now work together on the same products and issues and in the same sprints.
You created a new Scrum board based on this filter:
project in (A,B) ORDER BY Rank ASC
You must also check two settings to make sure the teams can access and use the new board.
Identify the two settings. (Choose two.)
They must now work together on the same products and issues and in the same sprints.
You created a new Scrum board based on this filter:
project in (A,B) ORDER BY Rank ASC
You must also check two settings to make sure the teams can access and use the new board.
Identify the two settings. (Choose two.)
A. application access of all team members
B. global permissions of all team members
C. availability of parallel sprints
D. sharing on the board sub-filter
E. sharing on the board filter
F. project permissions
Answer: EF
Question #7 (Topic: Exam A)
Your team needs a new board that:
only shows issues that are actively in progress
allows a separate area to prioritize incoming work
allows them to release issues from the Done column
Identify the correct solution to meet these requirements
only shows issues that are actively in progress
allows a separate area to prioritize incoming work
allows them to release issues from the Done column
Identify the correct solution to meet these requirements
A. Create a scrum board and enable the backlog.
B. Create a scrum board and configure swimlanes.
C. Create a kanban board and enable column constraints.
D. Create a scrum board and configure a quick filter.
E. Create a kanban board and enable the backlog.
F. Create a kanban board and configure swimlanes.
Answer: E
Question #8 (Topic: Exam A)
A team needs a board that meets these requirements:
All issues can be moved across the entire workflow on a single view of the board.
Issues can be worked in a continuous flow without start and stop dates.
Which board configuration meets the requirements?
All issues can be moved across the entire workflow on a single view of the board.
Issues can be worked in a continuous flow without start and stop dates.
Which board configuration meets the requirements?
A. Kanban board without backlog
B. Scrum board without parallel sprints
C. Scrum board with swimlanes
D. Kanban board with backlog
Answer: A
Question #9 (Topic: Exam A)
Newly created issues start in the To Do column of your Kanban board. The column has grown too full.
Additionally, the team is unable to focus on the prioritized issues they should be working on.
Which configuration change will help alleviate both problems?
Additionally, the team is unable to focus on the prioritized issues they should be working on.
Which configuration change will help alleviate both problems?
A. enable the Kanban backlog
B. use card colors to distinguish priorities
C. add the Priority field to the card layout
D. create a quick filter
Answer: A
Question #10 (Topic: Exam A)
DEV is a company-managed Kanban project with many statuses.
Users should never see issues in Cancelled or Rejected status when viewing their project board.
You want to remove the issues from the board but still have them counted in project reports.
Identify the approach that satisfies this requirement.
Users should never see issues in Cancelled or Rejected status when viewing their project board.
You want to remove the issues from the board but still have them counted in project reports.
Identify the approach that satisfies this requirement.
A. remove the statuses from the project workflow
B. add a board sub-filter to exclude the two statuses
C. exclude the two statuses from the board filter
D. hide the two statuses through a quick filter
E. create swimlanes for all the statuses except those two
Answer: B