Question #1 (Topic: Exam A)
Your company-managed kanban project has a total of six statuses in the workflows. Which statement about the kanban board is true?
A. The board must have at least six columns.
B. The board can include only statuses that are in every workflow.
C. The board can have multiple In Progress statuses, from different workflows, mapped to the same column.
D. The board must have the backlog and epic panel enabled.
Answer: C
Question #2 (Topic: Exam A)
5 development teams need to work across 3 projects and plan their iterations in a single board.
Which board supports this?
Which board supports this?
A. team-managed Kanban board
B. company-managed Kanban board
C. team-managed Scrum board
D. company-managed Scrum board
Answer: D
Question #3 (Topic: Exam A)
You are the project administrator of two Scrum projects, MOBI and TIS.
Team members find it difficult to switch between both projects to work on separate sprints.
They need the ability to work on issues from both projects in a single sprint.
Identify two ways that you can satisfy this requirement. (Choose two.)
Team members find it difficult to switch between both projects to work on separate sprints.
They need the ability to work on issues from both projects in a single sprint.
Identify two ways that you can satisfy this requirement. (Choose two.)
A. use the Filter Results dashboard gadget to show both MOBI and TIS issues
B. add a quick filter to the board in MOBI to show issues from TIS
C. create a new Scrum board that includes both MOBI and TIS issues
D. base swimlanes on MOBI and TIS projects
E. change the TIS project board filter to include issues from MOBI project
Answer: CE
Question #4 (Topic: Exam A)
Marcella can see TIS issues but not the TIS project board.
Identify the reason why.
Identify the reason why.
A. The board filter is not shared with Marcella.
B. The board filter excludes issues assigned to Marcella.
C. Marcella is not a board administrator.
D. Marcella is missing a project permission.
E. The board location has changed.
Answer: A
Question #5 (Topic: Exam A)
You shared a URL to the dashboard with Bobby but when he looks at it, the gadgets return errors that state, "The filter configured for this gadget could not be retrieved."
What is the most likely problem with the filters?
What is the most likely problem with the filters?
A. They return issues from team-managed projects.
B. They return issues with hidden fields.
C. They are not shared with Bobby.
D. They contain corrupt JQL clauses.
Answer: C