PMI PfMP - Portfolio Management Professional Exam

Question #11 (Topic: Exam A)
Which of the following should be included in a portfolio risk management plan? (Choose two.)
A. Dependencies B. Methodology C. Roles and responsibilities D. Key milestones and deliverables
Answer: BC
Question #12 (Topic: Exam A)
Which of the following are portfolio process assets?
A. List of portfolio components B. Portfolio budget C. Portfolio risk register D. All the above
Answer: D
Question #13 (Topic: Exam A)
A supply chain manager mentioned that the required materials for your portfolio might be out of stock next month due to coronavirus. What should you do next?
A. Analyze the impact on the portfolio B. Contact new vendors to provide materials C. Record the risk in a risk register D. Mention the risk in risk reports
Answer: C
Question #14 (Topic: Exam A)
You want to ask for more funding to improve deliverables’ quality because customers gave low reviews. Where should you include your recommendation?
A. Portfolio management plan B. Portfolio reports C. Portfolio dashboard D. Portfolio roadmap
Answer: B
Question #15 (Topic: Exam A)
The IT department of a company didn’t recognize that existing infrastructure could not handle a sudden increase in users. Now the online shop of that company is down due to a successful marketing campaign. How do you describe the current situation?
A. blocker B. issue C. missed opportunity D. risk
Answer: B