PRINCE2 PRINCE2-Re-Registration - PRINCE2 Re-Registration Exam
Page: 3 / 49
Total 244 questions
Question #11 (Topic: Volume A)
Why is a Project Brief produced?
A. To act as a trigger for the Starting up a Project process
B. To record the strategies and management controls to be used by a project
C. To provide a full and firm foundation for the initiation of a project
D. To be used by the Project Board as a basis for reviewing the progress of a project
Answer: C
Question #12 (Topic: Volume A)
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?]
through follow-on action recommendations.
through follow-on action recommendations.
A. the measurement of benefits NOT yet realized
B. the handover of products
C. open issues and risks
D. the release of resources
Answer: C
Question #13 (Topic: Volume A)
In what process is the authorization to deliver the project's products given?
A. Starting up a Project
B. Initiating a Project
C. Managing a Stage Boundary
D. Directing a Project
Answer: D
Question #14 (Topic: Volume A)
Which of the following is NOT part of quality planning?
A. Define quality responsibilities
B. Gain acceptance of the project product
C. Agree acceptance criteria
D. Set quality tolerances
Answer: B
Question #15 (Topic: Volume A)
Which should be provided by a project mandate?
A. Terms of reference
B. Detailed Business Case
C. Stage tolerances
D. Initiation Stage Plan
Answer: A