PRINCE2 PRINCE2-Re-Registration - PRINCE2 Re-Registration Exam
Page: 1  / 49
							Total 244 questions
						
								Question #1 (Topic:  Volume A)
								
							
							
																When considering risks, which describes an opportunity in a project?
								
																										
							
						
 A. An uncertain event that could have a negative impact on objectives 
 B. An uncertain event that could have a favourable impact on objectives 
 C. An event that has occurred resulting in a negative impact on objectives 
 D. An event that has occurred resulting in a favourable impact on objectives 
								
								
									Answer: B
								
								
								Question #2 (Topic:  Volume A)
								
							
							
																Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid,
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
								
																										
							
						1. The Project Manager has day-to-day control for a management stage within the limits laid,
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
 A. Only 1 is true 
 B. Only 2 is true 
 C. Both 1 and 2 are true 
 D. Neither 1 or 2 are true 
								
								
									Answer: C
								
								
								Question #3 (Topic:  Volume A)
								
							
							
																Which may be funded from a risk budget?
								
																										
							
						
 A. Corrections due to off-specifications 
 B. Impact analysis of requests for change 
 C. Implementation of a fallback plan 
 D. Preparation of the Risk Management Strategy 
								
								
									Answer: C
								
								
								Question #4 (Topic:  Volume A)
								
							
							
																What is the first task of product-based planning?
								
																										
							
						
 A. Produce the Initiation Stage Plan 
 B. Write the Project Product Description 
 C. Identify dependencies 
 D. Create the product breakdown structure 
								
								
									Answer: B
								
								
								Question #5 (Topic:  Volume A)
								
							
							
																How many tasks does the product-based planning technique describe?
								
																	
							
						
 A. One 
 B. Two 
 C. Three 
 D. Four 
								
								
									Answer: D