Question #11 (Topic: Question Set 10)
Which of the following management products ARE updated as part of Managing a stage boundary?
1. Business Case
2. Benefits Review Plan
3. Configuration Item Records
4. Project Brief
A. 1, 2, 3 B. 1, 3, 4 C. 1, 2, 4 D. 2, 3, 4
Answer: A
Question #12 (Topic: Question Set 10)
Which of the following activities could trigger the production of an exception plan?
A. Review Stage status B. Giving ad hoc direction C. Escalating a project issue D. Report stage end
Answer: B
Question #13 (Topic: Question Set 10)
Which of the following statements is FALSE regarding the Continued Business Justification?
A. The justification for the project must remain the same throughout the project. B. The justification for the project should remain vabd. C. The justification for the project may change. D. If the project is no longer justified it should be stopped.
Answer: A
Question #14 (Topic: Question Set 10)
Which of the following activities is NOT an action of preparing for planned closure?
A. Update the project plan with actual B. Update the Project Management Team C. Request a product status account D. Confirm project has delivered what is defined in Project Product Description
Answer: B
Question #15 (Topic: Question Set 10)
Which principle is supported by the activity Evaluate the Project?
A. Continued Business Justification B. Defined roles and responsibilities C. Learn from experience D. Manage by stages
Answer: C