PRINCE2 PRINCE2-Practitioner Edition 6 - PRINCE2 Practitioner Edition 6 Exam
Page: 2 / 75
Total 374 questions
Question #6 (Topic: Question Set 1)
Which of the following activities is the Executive responsible for?
A. Ensure the desired outcome of the project is specified
B. Responsible for the benefits review plan
C. Assess and update the Business Case at the end of each stage
D. Responsible for the Benefits Review Plan post project
Answer: B
Question #7 (Topic: Question Set 1)
DRAG DROP
BUSINESS CASE
Here are three statements from the business case for the Health and Safety Project.
Under which heading in the business case (A-F) should they be recorded?
Choose only one heading for each statement. Each heading can be used once, more than once, or not at all.
Select and Place:

BUSINESS CASE
Here are three statements from the business case for the Health and Safety Project.
Under which heading in the business case (A-F) should they be recorded?
Choose only one heading for each statement. Each heading can be used once, more than once, or not at all.
Select and Place:

Answer:

Question #8 (Topic: Question Set 1)
The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning
course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will be entered into the business
case.
Why is the executive's decision to deliver the benefits early appropriate for managing the business case?
course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will be entered into the business
case.
Why is the executive's decision to deliver the benefits early appropriate for managing the business case?
A. Because organizations with mature project management often include the early justification for the project in the business case.
B. Because the outputs being delivered incrementally will be beneficial and will allow the business case to be justified.
C. Because one of the PRINCE2 principles is that a project should focus on products to deliver the outputs early.
D. Because the business case should be updated after every increment of the 'e-learning course'.
Answer: B
Question #9 (Topic: Question Set 1)
During stage 3, the project scope was extended to include a practice test for learners to take during the training course. The cost of this test will be included in the
cost of the course.
The change to project scope was approved and the cost of ֲ£2,500 was paid for from the change budget. The project manager documented an increase of ֲ£2,500
in the project budget in the business case.
Is this an appropriate action, and why?
cost of the course.
The change to project scope was approved and the cost of ֲ£2,500 was paid for from the change budget. The project manager documented an increase of ֲ£2,500
in the project budget in the business case.
Is this an appropriate action, and why?
A. Yes, because the justification for the project should be recalculated based on the revised project budget.
B. Yes, because the project manager determines which costs need to be updated at the end of each stage
C. No, because the use of the change budget means that the project budget does not need to be increased.
D. No, because changes to operational costs post-project should have been included in the business case.
Answer: C
Question #10 (Topic: Question Set 10)
When updating the project plan as part of Managing a stage boundary, what else might be updated?
A. Exception Plan
B. Project Management team
C. Business Case
D. Project Initiation Documentation
Answer: C