Once the project's WBS has been created what process may happen next?
Answer : B
Explanation:
The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time.
Incorrect Answers:
A: Estimating activity resources is dependent on the activity list, so this choice is not valid.
C: Estimate activity durations are dependent on the activity list, so this choice is not valid.
D: Sequencing the activities cannot happen until the activity list has been created.
Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
Answer : A
Explanation:
The Precedence Diagramming Method uses both predecessors and successors as nodes in the project network diagram. The PDM approach is the most common network diagram approach used.
Incorrect Answers:
B: The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram.
C: Dependency determination identifies the order of the project work.
D: Activity on the node places activities on circles within a network diagram. It is an example of the precedence diagramming method.
You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?
Answer : A
Explanation:
Performance reports are distributed through the push technique. This means that the project manager distributes the reports regularly through a mechanism, such as email.
Incorrect Answers:
B: Many-to-many technique describes a conversation between many people.
C: One-to-one technique describes a conversation between two people.
D: A pull technique describes the recipients of the report "pulling" the information, such as from a Website.
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project.
The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?
Answer : C
Explanation:
Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce project risks.
Incorrect Answers:
A: Resource leveling can actually increase the project duration.
B: Crashing can reduce the project duration but it increases the labor expense, something the stakeholders won't approve.
D: Removing things from the project scope can reduce the project duration, but it will not satisfy the requirements the stakeholders have identified.
The Define Activities process is the first process in the project time management knowledge area. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?
Answer : D
Explanation:
Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the following:
-> Activity list
-> Activity attributes
-> Resource calendars
Incorrect Answers:
A: The activity list is an output of the define activities process.
B: The milestone list is an output of the define activities process.
C: The activity attributes is an output of the define activities process.