Question #11 (Topic: Topic 1)
Which input to the Manage Stakeholder Engagement process is used to document
changes that occur during the project?
changes that occur during the project?
A. Issue log
B. Change log
C. Expert judgment
D. Change requests
Answer: B
Question #12 (Topic: Topic 1)
An input to the Plan Stakeholder Management process is:
A. The project charter.
B. The stakeholder analysis.
C. Acommunication management plan.
D. Astakeholder register.
Answer: D
Question #13 (Topic: Topic 1)
An input to the Plan Cost Management process is:
A. Cost estimates.
B. Resource calendars,
C. The project charter,
D. The risk register.
Answer: C
Question #14 (Topic: Topic 1)
A technique used to determine the cause and degree of difference between baseline and
actual performance is:
actual performance is:
A. Product analysis.
B. Variance analysis.
C. Document analysis,
D. Decomposition.
Answer: B
Question #15 (Topic: Topic 1)
The process of identifying and documenting project roles, responsibilities, required skills,
and reporting relationships and creating a staffing management plan is known as:
and reporting relationships and creating a staffing management plan is known as:
A. Develop Project Team.
B. Manage Project Team.
C. Acquire Project Team.
D. Plan Human Resource Management.
Answer: D