Question #6 (Topic: Topic 1)
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA),
and trend analysis are examples of which tool or technique?
and trend analysis are examples of which tool or technique?
A. Expert judgment
B. Forecasting methods
C. Earned value management
D. Analytical techniques
Answer: D
Question #7 (Topic: Topic 1)
The Perform Quality Assurance process occurs in which Process Group?
A. Executing
B. Monitoring and Controlling
C. Initiating
D. Planning
Answer: A
Question #8 (Topic: Topic 1)
Enterprise environmental factors are an input to which process?
A. Control Scope
B. Define Scope
C. Plan Scope Management
D. Collect Requirements
Answer: C
Question #9 (Topic: Topic 1)
Which process develops options and actions to enhance opportunities and reduce threats
to project objectives?
to project objectives?
A. Identify Risks
B. Control Risks
C. Plan Risk Management
D. Plan Risk Responses
Answer: D
Question #10 (Topic: Topic 1)
The process of establishing the policies, procedures, and documentation for planning,
developing, managing, executing, and controlling the project schedule is known as:
developing, managing, executing, and controlling the project schedule is known as:
A. Plan Schedule Management.
B. Develop Project Charter.
C. Develop Schedule.
D. Plan Scope Management.
Answer: A