PMI PMI-001 - Project Management Professional v5 Exam
Page: 2  / 184
							Total 919 questions
						
								Question #6 (Topic: Topic 1)
								
							
							
																Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA),
and trend analysis are examples of which tool or technique?
								
																										
							
						and trend analysis are examples of which tool or technique?
 A. Expert judgment 
 B. Forecasting methods 
 C. Earned value management 
 D. Analytical techniques 
								
								
									Answer: D
								
								
								Question #7 (Topic: Topic 1)
								
							
							
																The Perform Quality Assurance process occurs in which Process Group?
								
																										
							
						
 A. Executing 
 B. Monitoring and Controlling 
 C. Initiating 
 D. Planning 
								
								
									Answer: A
								
								
								Question #8 (Topic: Topic 1)
								
							
							
																Enterprise environmental factors are an input to which process?
								
																										
							
						
 A. Control Scope 
 B. Define Scope 
 C. Plan Scope Management 
 D. Collect Requirements 
								
								
									Answer: C
								
								
								Question #9 (Topic: Topic 1)
								
							
							
																Which process develops options and actions to enhance opportunities and reduce threats
to project objectives?
								
																										
							
						to project objectives?
 A. Identify Risks 
 B. Control Risks 
 C. Plan Risk Management 
 D. Plan Risk Responses 
								
								
									Answer: D
								
								
								Question #10 (Topic: Topic 1)
								
							
							
																The process of establishing the policies, procedures, and documentation for planning,
developing, managing, executing, and controlling the project schedule is known as:
								
																	
							
						developing, managing, executing, and controlling the project schedule is known as:
 A. Plan Schedule Management. 
 B. Develop Project Charter. 
 C. Develop Schedule. 
 D. Plan Scope Management. 
								
								
									Answer: A
								
								 
							 
									