ITIL P3OF - Portfolio, Programme and Project Offices® Foundation Exam

Question #6 (Topic: Topic 1)
Which is a key activity of the Identify' process in the permanent P3O lifecycle?
A. Delivering the new capability B. Planning tranches of delivery C. Analysing stakeholders and planning communications D. Assessing the current state of P3O provision
Answer: D
Question #7 (Topic: Topic 1)
Which role is responsible for developing a Portfolio Dependencies Register?
A. Programme Specialist B. Portfolio Analyst C. Reporting D. Tools Expert
Answer: B
Question #8 (Topic: Topic 1)
Which is an activity in the definition and implementation of a temporary Programme Office?
A. Create a Vision Statement for the office B. Transfer the realization of benefits to the operational environment C. Identify existing processes defined by the COE that may used D. Design the future state Blueprint
Answer: C
Question #9 (Topic: Topic 1)
What model has permanent decentralized offices with temporary Programme Offices, as
required?
A. P3O with Hub Portfolio Offices B. P3O with Organization Portfolio Office C. P3O with Temporary Offices D. Virtual P3O
Answer: A
Question #10 (Topic: Topic 1)
Which describes how P3M3 assessments are used when implementing a P3O?
A. Document new processes to be followed B. Define the skills needed in the implementation team C. Develop a tranche-based plan that suits maturity levels D. Assess project or programme complexity
Answer: C