Microsoft MB6-700 - Microsoft Dynamics AX 2012 R2 Project Exam
Page: 3 / 15
Total 75 questions
Question #11 (Topic: )
What is the difference between advanced and simple internal projects?
A. Advanced internal projects can track expense transactions; simple internal projects cannot.
B. Advanced internal projects can use work in process (WIP) to post costs; simple internal projects cannot.
C. Advanced internal projects can track hour transactions; simple internal projects cannot.
D. Advanced internal projects allow on-account posting; simple internal projects do not.
Answer: B
Question #12 (Topic: )
You work with a fixed-price project.
To which process do the completed contract and completed percentage assessment
principles relate?
To which process do the completed contract and completed percentage assessment
principles relate?
A. Posting revenue
B. Transferring costs from balance sheet to profit and loss accounts
C. Posting costs
D. Accumulating costs in balance sheet accounts
Answer: A
Question #13 (Topic: )
You attach an invoice format to the project contract. Which item is controlled by the invoice
format setting?
format setting?
A. Invoice output destination
B. Invoice currency
C. Invoice summarization
D. Invoice orientation
Answer: C
Question #14 (Topic: )
Your company negotiates a project contract worth 120,000 USD with a customer. To
maintain an acceptable profit margin,the budget for the project is set at 85,000 USD.
The project manager wants to manage the project as three related subprojects,so you
divide the total budget into 25,000 USD,40,000 USD,and 20,000 USD. When you create
the root project,you create the original budget and submit the budget to workflow for
approval.
How should you manage the budgeting for the entire project hierarchy?
maintain an acceptable profit margin,the budget for the project is set at 85,000 USD.
The project manager wants to manage the project as three related subprojects,so you
divide the total budget into 25,000 USD,40,000 USD,and 20,000 USD. When you create
the root project,you create the original budget and submit the budget to workflow for
approval.
How should you manage the budgeting for the entire project hierarchy?
A. Manage the budgeting only at the subproject level in the project hierarchy.
B. Manage the budgeting as a single unit for the entire project hierarchy.
C. Manage the budgeting separately for each project type in the project hierarchy.
D. Manage the budgeting separately for each subproject in the project hierarchy.
Answer: B
Question #15 (Topic: )
You set up the project validation feature.
You need to restrict certain employees to use specific categories when they enter
transactions in journals for particular projects.
Which type of validation group should you configure?
You need to restrict certain employees to use specific categories when they enter
transactions in journals for particular projects.
Which type of validation group should you configure?
A. Worker/project
B. Categories
C. Projects
D. Project/category
E. Worker/category
Answer: D