HP HPE0-S54 - Designing HPE Server Solutions Exam

Question #11 (Topic: Topic 1)
You have a customer who has thousands of ProLiant servers spanning Gen8, Gen9, and Gen10 across multiple server models (Rack, Tower, Blade, Apollo), all
licensed with iLO Advanced. The customer needs an effective way to inventory and update the firmware across the environment.
Which tool should you recommend?
A. iLO Amplifier Pack B. OneView C. Intelligent Provisioning D. SUM (System Update Manager)
Answer: A
Question #12 (Topic: Topic 1)
Refer to the exhibit.
[HP-HPE0-S54-1.0/xmlfile-7_1.png]
You are installing three Synergy frames for a customer PoC in the configuration shown. The composer is unable to discover the frames.
What is the most likely cause of the problem?
A. Another composer is needed Frame 3 B. Composer 2 is in the wrong frame C. The management network should be connected to the top and bottom frames D. The management ring should be connected using the FLM link ports
Answer: A
Question #13 (Topic: Topic 1)
A customer has 10 HPE BladeSystem enclosures managed by HPE OneView. They want to add three HPE Synergy frames.
What is a proper procedure to manage a new HPE Synergy installation?
A. Use HPE Composer for HPE Synergy frames management B. Deploy HPE Global Dashboard for HPE Synergy management C. Add all frames to the existing HPE OneView appliance D. Deploy a dedicated HPE OneView appliance for HPE Synergy frames
Answer: B
Question #14 (Topic: Topic 1)
A customer needs a VDI solution. The amount of compute per U of rack space will be a key point in their solution selection.
Which HPE product would be an ideal solution as part of your RFP response?
A. HPE Apollo 4510 Gen10 B. HPE Apollo 4200 Gen9 C. HPE SY480 Gen10 D. HPE DL580 Gen10
Answer: A
Question #15 (Topic: Topic 1)
What are features of the HPE Synergy Planning Tool? (Choose two.)
A. It creates a REST configuration file based on configuration created B. It recommends the best top-of-rack switch C. It provides estimated power consumption and weights of the solution D. It runs on the Partner Ready Portal E. It aids configuration of rack, Frames, compute, storage, fabric and power
Answer: CE
Download Exam
Page: 3 / 22
Total 109 questions