Question #11 (Topic: Exam A)
What is the objective of a Sprint Retrospective meeting?
A. Provide feedback to the project sponsor.
B. Prepare for Quality Gate.
C. Improve the team's process.
D. Prioritize the remaining backlog items.
Answer: C
Question #12 (Topic: Exam A)
What are potential use cases for SAP Cloud ALM? (Choose two.)
A. Implementing Tricentis Test Automation
B. Implementing SAP Ariba
C. Upgrading SAP Success Factors
D. Upgrading SAP S/4HANA Public Edition
Answer: CD
Question #13 (Topic: Exam A)
What are some of the key topics covered in the Customer Team Enablement workstream? (Choose two.)
A. Business process expertise
B. Project management expertise
C. Process benchmarking expertise
D. Technology and architecture expertise
Answer: AB
Question #14 (Topic: Exam A)
When do you perform Quality Gate (Q-Gate) during a project? (Choose two.)
A. At the end of Realize phase
B. At the end of Run phase
C. At the end of Prepare phase
D. At the end of Discover phase
Answer: AC
Question #15 (Topic: Exam A)
Which accelerators support the fit-to-standard workshop in the Explore phase? (Choose two.)
A. Quality Gate Checklist
B. Backlog Template
C. Test Strategy
D. Business Process Design Template
Answer: BD