SAP E_ACTAI_2403 - SAP Certified Specialist - Project Manager - SAP Activate for Agile Implementation Management Exam
Page: 2 / 8
Total 40 questions
Question #6 (Topic: Exam A)
What activity do you perform in the Deploy phase?
A. Complete integration testing
B. Final assessment of data quality
C. Perform productive cutover
D. Implement operations processes
Answer: C
Question #7 (Topic: Exam A)
What accelerator can help you document the configuration definition in the Explore phase?
A. Business Driven Configuration Questionnaire
B. Data definition
C. Business Blueprint document
D. Backlog template
Answer: A
Question #8 (Topic: Exam A)
What information does the Scrum team need before they can correctly estimate the relative size of backlog user stories? (Choose two.)
A. Anchor user story in the backlog
B. Number of backlog user stories
C. Definition of Ready
D. Definition of Done
Answer: AC
Question #9 (Topic: Exam A)
Which of the following belong to the Application Design and Configuration workstream in the Explore phase? (Choose two.)
A. Change Impact Analysis
B. Integration prerequisites confirmation
C. Configuration definition
D. Fit-to-standard workshop
Answer: BC
Question #10 (Topic: Exam A)
Which of the following are included in ready-to-use content in SAP Activate? (Choose two.)
A. SAP Best Practices
B. Baseline Activation Service
C. Project accelerators
D. Business models from leading companies in each industry sector
Answer: AC