IBM C2140-820 - Rational Team Concert V4 Exam

Question #11 (Topic: )
A customer expects a work item with an appropriate "Planned for" attribute to show on a
team's iteration plan, but the work item is missing from the plan view. What is the most
likely reason?
A. The work item's owner is unassigned. B. The work item's owner is not part of the team owning the plan. C. The work item's Filed Against category is not associated to the team owning the plan. D. The work item's due dateis set to a date after the iteration's end date.
Answer: C
Question #12 (Topic: )
What is associated with a project area and is a collection of practices, rules, and
guidelines?
A. process B. Team area C. work item D. rule set
Answer: A
Question #13 (Topic: )
Which three Rational Team Concert clients support reporting? (Choose three.)
A. RTC client for Microsoft Visual Studio IDE B. RTC web client C. RTC Eclipse client D. RTC context-aware search tool E. RTC commande-line interface
Answer: A,B,C
Question #14 (Topic: )
What does the filled-in shape icon shown below indicate in Team Artifacts view?
A. Files in that component have been checked out. B. All files from that component have been loaded into a local sandbox. C. There are incoming changes in thatcomponent. D. There are outgoing changes in that component.
Answer: B
Question #15 (Topic: )
A work item appears in a plan when which two conditions are met? (Choose two.)
A. The Filed Against field has the work item category linked to the team area that ownsthe plan. B. The Due Date field of the work item is on or before the end date of the plan. C. The work item is assigned to a member of the team that owns the plan. D. The Planned For field in the work item matches the Iteration field of the plan. E. The work item is created by a member of the team area that owns the plan.
Answer: A,D
Download Exam
Page: 3 / 12
Total 60 questions