IBM C2140-820 - Rational Team Concert V4 Exam
Page: 2 / 12
Total 60 questions
Question #6 (Topic: )
What is the repository workspace?
A. a server-side entity that tracks items that have been placed under source control
B. a local workspace that holds a copy of specific sets of file versions that arestored in Rational Team Concert
C. the Eclipse workspace used when Rational Team Concert is launched by using the Eclipse client
D. the local copy of the latest file versions on a Rational Team Concert stream
Answer: A
Question #7 (Topic: )
Which capabilitiesdoes Rational Team Concert support out-of-the-box?
A. process configuration, reporting, and business process management
B. task tracking, planning, and source control management
C. build automation, performance testing, and test virtualization
D. planning, real time dashboards, and use-case modeling
Answer: B
Question #8 (Topic: )
A project manager is creating a new plan view and does not like the default display. What
are the other plan view display options?
are the other plan view display options?
A. Work Breakdown, Taskboard, and Roadmap
B. Load,Progress (Hours), and Progress (Size)
C. Tree, Bars, and Folder
D. Tree, Taskboard, and Kanban
Answer: D
Question #9 (Topic: )
Roles can be defined at which levels?
A. project and timelines
B. project and team area
C. team area and timelines
D. Iteration and release
Answer: B
Question #10 (Topic: )
How do you make use of a process template?
A. By adding the team members to the process template
B. By specifying the process template when you create a project area.
C. By associating a process template to the current iteration.
D. By creating a process template category for the project
Answer: B