IBM C2140-820 - Rational Team Concert V4 Exam

Question #1 (Topic: )
What are two types of work item approvals? (Choose two.)
A. approval B. certification C. review D. validation E. confirmation
Answer: A,C
Question #2 (Topic: )
Which attribute is used to assign a work item to a team area?
A. owner B. category C. component D. stream
Answer: B
Question #3 (Topic: )
What is the Jazz Team Build component?
A. A component that provides buildawareness to the team B. A component that helps you create a team for a new project C. A component that provides reporting capabilities from a data warehouse D. A component that helps you manage versions of source files
Answer: A
Question #4 (Topic: )
In a work item comment, what is happening when "@" followed by a user ID (for example,
"@clara") is added?
A. The addressee receives a notification that she was mentioned in the comment. B. The work item is automatically assigned to the addressee. C. A review is created, and the addressee is added as a reviewer. D. The comment is only visible to the addressee that is mentioned.
Answer: A
Question #5 (Topic: )
What are three ways builds are scheduled and initiated? (Choose three.)
A. at a continuous interval in minuteson selected days B. at a particular time for defined days C. by a user with appropriate permissions D. automatically after a user saves a change E. By adding the keyword "@build"in a work item comment
Answer: A,B,C
Download Exam
Page: 1 / 12
Total 60 questions