SAP C_TS413_2021 - SAP Certified Application Associate - SAP S/4HANA Asset Management Exam

Question #1 (Topic: Topic 1. Preventive Maintenance )
The technical completion of the current maintenance order was posted with a delay of 5 days.
What happens to the next planned date if you set the shift factor for early completion to 100%?
A. It is postponed by a full cycle (100%). B. It is postponed by 5 days. C. It is not shifted. D. It will be 5 days earlier.
Answer: C
Question #2 (Topic: Topic 1. Preventive Maintenance )
What can be determined using the offset within a maintenance strategy?
A. The basic start date of the maintenance order B. The call date for the maintenance order C. The first due date of a maintenance package D. The scheduled start date of the maintenance order
Answer: C
Question #3 (Topic: Topic 1. Preventive Maintenance )
Which scheduling parameters are used in a multiple-counter plan? (Choose two.)
A. Scheduling period B. Start date C. Scheduling indicator D. Factory calendar
Answer: AB
Question #4 (Topic: Topic 1. Preventive Maintenance )
How does a performance-based maintenance plan calculate the interval between start date and planned date?
A. Cycle length divided by annual performance B. Cycle length divided by ((scheduling period) x (cycle modification factor)) C. Cycle length divided by monthly performance D. Cycle length divided by (annual performance / 365)
Answer: D
Question #5 (Topic: Topic 1. Preventive Maintenance )
The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100%. Which date is relevant for the calculation of future planned dates if the maintenance work is delayed?
A. Planned end date of the maintenance order B. Actual finish date of the maintenance order C. Planned date of the next call, independent of maintenance order dates D. Technical completion date of the maintenance order
Answer: D