SAP C_TS413_2021 - SAP Certified Application Associate - SAP S/4HANA Asset Management Exam
Page: 2 / 16
Total 80 questions
Question #6 (Topic: Topic 1. Preventive Maintenance
)
Which of the following parameters are available when you define a new maintenance plan category? (Choose three.)
A. Completion date
B. Call object
C. Change documents
D. Order type
E. Maintenance activity type
Answer: ABC
Question #7 (Topic: Topic 1. Preventive Maintenance
)
You want to create a single-cycle plan with a cycle of 12 months. You use the scheduling indicator Time - key date.
The orders should be called 3 months before the planned date.
How can you set up the maintenance plan? (Choose two.)
The orders should be called 3 months before the planned date.
How can you set up the maintenance plan? (Choose two.)
A. Set the call horizon to 90 days.
B. Set the call horizon to 25%.
C. Set the call horizon to 75%.
D. Set the offset to 3 months.
Answer: B
Question #8 (Topic: Topic 1. Preventive Maintenance
)
You want to set up a general maintenance task list for inspection rounds using the overall time confirmation as a simplified way to record measurement documents. What do you need to do? (Choose two.)
A. Assign a measuring point as a production resources/tools (PRT) to a task list operation.
B. Assign a piece of equipment with an allocated measuring point to a task list operation.
C. Assign an inspection document as a PRT to the task list operation.
D. Assign an inspection lot to the task list header.
Answer: AB
Question #9 (Topic: Topic 1. Preventive Maintenance
)
You create two maintenance packages and only one package should be executed at a time. Which parameter determines this?
A. Lead flow
B. Hierarchy
C. Cycle set sequence
D. Package sequence
Answer: A
Question #10 (Topic: Topic 1. Preventive Maintenance
)
You want to set up a scenario for regular maintenance. The first event should take place after 1 year; after that, it is a regular cycle of 6 months.
Which parameter do you have to use to map this in the system?
Which parameter do you have to use to map this in the system?
A. Maintenance package offset
B. Maintenance plan category
C. Shift factor
D. Scheduling indicator
Answer: A