SAP C_ACT_2403 - SAP Certified Associate - Project Manager - SAP Activate Exam

Question #11 (Topic: Topic 1, Agile Project Planning )
What technique helps a Scrum team to prioritize a large, flat backlog? (Choose two.)
A. MoSCoW prioritization B. User story mapping C. A/B testing user stories D. Splitting the backlog into epics
Answer: AB
Question #12 (Topic: Topic 2, Agile Project Delivery )
Which of the following is a key characteristic of the Agile project approach?
A. Frequent quality gates in each sprint B. Iterative build with frequent inspections C. Frequent and detailed release scheduling D. Higher business involvement in the early phases
Answer: B
Question #13 (Topic: Topic 2, Agile Project Delivery )
What do you do during the sprint retrospective meeting?
A. Discuss best practices with the Scrum Team. B. Define sprint activities and best practices with the customer. C. Plan future sprints with the customer. D. Document best practices guided by the Scrum Master.
Answer: A
Question #14 (Topic: Topic 2, Agile Project Delivery )
How do you set up Scrum teams? (Choose two.)
A. By type of work, like configuration Scrum, documentation Scrum, and testing Scrum. B. Based on group size, but a minimum of 12 people. C. Based on end-to-end processes like order-to-cash. D. As a cross-functional team covering multiple functions, like configuration, data loads, and testing.
Answer: CD
Question #15 (Topic: Topic 2, Agile Project Delivery )
When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?
A. During the sprint retrospective B. During the sprint user acceptance test C. During the sprint backlog review D. During the sprint review
Answer: D