SAP C_ACT_2403 - SAP Certified Associate - Project Manager - SAP Activate Exam

Question #6 (Topic: Topic 1, Agile Project Planning )
What information does the project team need before they can correctly estimate the relative size of backlog user stories? (Choose two.)
A. Available project resources B. Definition of Ready C. Definition of Done D. Benchmark user story
Answer: BD
Question #7 (Topic: Topic 1, Agile Project Planning )
In which phase do you collect the main functional attributes of the product as per the Agile definition?
A. Realize B. Discover C. Prepare D. Explore
Answer: D
Question #8 (Topic: Topic 1, Agile Project Planning )
Comparing the SAP Activate methodology with Waterfall, what activities are performed by the new project roles?
A. Scrum master and project sponsor to define project charter B. Product owner to discuss schedule with the customer C. Scrum team to review best practices D. Scrum master to prepare the project plan
Answer: C
Question #9 (Topic: Topic 1, Agile Project Planning )
When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?
A. Sprint planning and sprint durations should be defined for the first 2 to 3 sprints. B. Realize phase scope, planning, and budget should be completed and final. C. User stories on product backlog should be in ready state for the first 2 to 3 sprints. D. Release plan and sprint ceremony guidelines should be finalized.
Answer: C
Question #10 (Topic: Topic 1, Agile Project Planning )
What criteria does the Scrum team use to sequence the product backlog? (Choose two.)
A. Experience of team members B. Length of the sprint C. Business priority D. Technical dependencies
Answer: CD