SAP C_ACT_2403 - SAP Certified Associate - Project Manager - SAP Activate Exam

Question #1 (Topic: Topic 1, Agile Project Planning )
Which activity helps the project team identify and add user stories to the backlog?
A. Conducting the fit-to-standard workshop B. Assessing documentation requirements C. Planning the release and sprints D. Benchmarking current business processes
Answer: A
Question #2 (Topic: Topic 1, Agile Project Planning )
Which of the following considerations apply when determining the project methodology? (Choose three.)
A. Organizational fit B. Project Manager fit C. Readiness fit D. Project fit E. Integration fit
Answer: ACD
Question #3 (Topic: Topic 1, Agile Project Planning )
Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?
A. Relative effort estimate in Ideal Person Days that reflects the best estimate by the Project Team B. Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity C. Product Owner's relative effort estimate that will be needed to implement and test the user story D. Detailed bottom-up effort estimate by the Product Owner that breaks up each story into short tasks
Answer: A
Question #4 (Topic: Topic 1, Agile Project Planning )
What are the responsibilities of the product owner in release and sprint planning? (Choose two.)
A. Analyze the functional and technical dependencies between user stories. B. Estimate the backlog user stories. C. Prioritize backlog user stories by business priority. D. Define objectives for each release.
Answer: CD
Question #5 (Topic: Topic 1, Agile Project Planning )
What is Scrum of Scrums?
A. Integration meeting among the various Scrum teams B. Inspection of code and configuration prior to sprint demo C. Alternative to regular Scrum process for a very large team D. Scrum team led by very experienced Scrum master
Answer: A